Tideway Project at
Carnwath Road
London
Background
FLI Precast Solutions Ltd was contracted to Design, Manufacture and Supply Bespoke Walls and Triangular Benching Blocks for the JV working on the Western contract of the Tideway Project at Carnwath Road.
We worked closely with our client to understand the project constraints including logistics, weight restrictions, tolerances and timeframes.
We designed bespoke freestanding walls 9.5m high to form the lower part of the benching mass concrete structure.
This included scabbled surfaces to the front to align with the shaft benching levels and dowels to the rear to tie into the mass concrete fill.
For the next stage of the works the benching blocks were installed in 3 rows with mass concrete fill behind each row.
Due to the tolerances and to achieve the geometry and alignment required each unit was modelled and individual moulds were created for each unit.
There were 30 bespoke shapes created ranging up to 26T in weight.
We look forward to updating you as the project progresses.
Project name: Thames Tideway Carnwath Rd Shaft Mass Benching
Location: London
Duration: 9 Months
Services provided:
Product(s): Bespoke
Contract partners/client (if applicable): BMBJV
At a Glance..



Looking to discuss a project?
Engineer or Quantity Surveyor
National Body or Local Authority
General Enquiry
Engineer or Quantity Surveyor
National Body or Local Authority
General Enquiry
Get a Quotation